Updated 18 June 2012,
Listen to audio of Radio Australia here.
The report outlines poor construction, botched surveys leading
to the evictions of families, infighting between contractors, delays and
cost overruns.
The $143 million Rail Rehabilitation Project is to
rehabilitate or build 641 kilometres of track, with the aim of
integrating Cambodia with a regional network including Vietnam and
Thailand.
But it has also attracted criticism by NGOs who say the
project has dealt poorly with displaced communities who were living
alongside the tracks.
Presenter: Liam Cochrane
Speaker: Nora Lindstrom, Progarmme Development Manager with Sahmakum Teang Tnaut